Scrum Methodology
Learn the Scrum Methodology
The Scrum methodology of agile software development marks a dramatic departure from waterfall management. In fact, Scrum and other agile processes were inspired by its shortcomings. The Scrum methodology emphasizes communication and collaboration, functioning software, and the flexibility to adapt to emerging business realities — all attributes that suffer in the rigidly ordered waterfall paradigm.
10th
NOV
Scrum Acceptance Criteria
Posted by admin under Scrum Basics
In Scrum, a Product Owner would never deem a team’s work “done/done/done” until he or she had consulted the story’s acceptance criteria. Acceptance criteria are the requirements that have to be met for a story to be assessed as complete. Acceptance criteria are incredibly important in Scrum because they spell out what a Product Owner expects and what a team needs to accomplish. There are no hairs to split and no points to argue. If it’s in the acceptance criteria, then it needs to be in the release.
So what happens when only some—most, even—of a story’s acceptance criteria is met? Should the team be awarded a corresponding percentage of the story points? Well, no. Scrum frowns on partial credit for work that is only partially completed. All of the criteria must be fulfilled or else the work is incomplete. (Many ScrumMasters won’t allow teams to present work that hasn’t been completed.)
Why does Scrum only accept work that is 100 percent complete? First of all, an implicit acceptance criterion of any story is that it must be completed during the sprint it was assigned. Work is confined to the sprint, so a team must complete the work in that sprint as well. Second, it’s common for teams to discover the final one percent of work to be more challenging than they expected. It might sound like a Yogi Berra-ism, but if it’s not done, it’s not done. Third, when a Product Owner awards unearned credit, it results in velocity inflation, rendering the team’s velocity an unreliable metric for forecasting. Furthermore, when a team is awarded credit for a story that it will have to finish in the next sprint, it means the team’s workload is even greater than the sprint backlog suggests. When this happens, a team has to play catch up, which often leads to a team falling behind and accruing substantial technical debt along the way.
Clearly, it is in the interest of the team to only award credit when it is completely earned. Partial credit only serves to undermine a Product Owner’s ability to forecast accurately and risks building technical debt.
Comments Feed Reader's Comments
Leave a Reply
Recent Posts
- Scrum based funding model – 20 percent May 9, 2013
- What is Agile ALM April 2, 2013
- MJは6月と7月の2ヶ月間、日本に滞在する予定です。スクラムのコーチングまたはトレーニングに興味のある方は是非ご連絡ください。 March 14, 2013
- The Next Big Idea March 5, 2013
- On Being Available February 17, 2013
Events
Click to Follow Laszlo on Twitter
Archives
- May 2013
- April 2013
- March 2013
- February 2013
- January 2013
- December 2012
- November 2012
- October 2012
- January 2012
- December 2011
- November 2011
- October 2011
- November 2010
- September 2010
- June 2010
- April 2010
- March 2010
- February 2010
- December 2009
- November 2009
- October 2009
- September 2009
- August 2009
- July 2009
- June 2009
- May 2009
- April 2009
- March 2009
- February 2009
- January 2009
- December 2008
- November 2008
- October 2008
- September 2008
- August 2008


Can you make a recommendation for a great book on Acceptance Criteria and how to write good acceptance criteria.
[...] demo a story that isn’t finished, or which doesn’t meet a definition of done, the team won’t demo one that doesn’t meet its Acceptance Criteria. Demo criteria can be especially important on [...]
[...] is completed. A good approach to define when you are really done with a story is to define some acceptance criteria for it. Then you check if the application meets these criteria to determine if the story you are [...]